Augustine Preparatory Academy Project
Milwaukee, WI
Project Overview
The Augustine Preparatory Academy project was a 200,000 sq. foot private school built to accommodate 1,700 students. We began the steel detailing process, which included all steel shop drawings, automated fabrications files and BIM model in February of 2016 with the majority of shop drawings submitted within 6 weeks.
Have a project you'd like to discuss?
PROJECT STATISTICS
Size of Project:
200,000 sq. feet
Structural Steel Used:
800+ Tons of structural steel as well as precast and long span joists
Cost of Project:
$53 Million